Kitchen

We have just made our last visit to inspect the building progress at Craig Cottage before our one-way trip down from Aberdeen. The kitchen is now mostly installed but still needs the granite counter tops installing with the sink and hob. There are some cupboard doors and drawer fronts that needed replacing but they should be arriving this week.

The floor tiling is all done now but still needs grouting. The kitchen floor tiles are covered with a protective sheet while the rest of the kitchen installation is taking place.

 

The bathroom tiling is almost complete and the rest of the bathroom fittings should be installed this week. This is the en-suite bathroom for the master bedroom.

 

 

We managed to save the old inner doors from the back porch and they have now been re-installed into their original position. There are also some old coat-hooks from the original cottage that should be re-mounted on the inner hall wall just opposite the doors.

 

 

 

 

The fitted wardrobes are installed in two of the bedrooms and ready for painting. Just inside the front door is a coat cupboard which is really nice and warm as it also houses the under-floor heating manifolds. Here are the master bedroom wardrobes where the painters have just got started on undercoating the insides.


After leaving Aberdeen in heavy rain this morning it was a pleasant surprise to find relatively warm, sunny weather down at Craig Cottage.  We had a wander round the garden as the sun was setting. Here’s the view from outside the sun room.

December sun illuminating the beach, lower garden and house.

Floor Tiles

There has been more building activity in the last couple of weeks despite the terrible weather. The kitchen and sun room floors are now tiled and looking good. The same tiles will be used through the hallway and into the utility room.

The bookshelves are being installed along the main corridor and most of the lighting is now installed. The heating is turned on and it is nice and cosy in the house now. The joiners are busy with finishing the trim around the doors and have started on the built-in wardrobes in one of the bedrooms.

 

The paving and gravel around the house has been completed. This is the small courtyard and path leading to the main house door. We will be planting up the soil bed with shade tolerant plants such as hosta and cyclamen as well as a selection of bulbs. We need something that will spread itself over the prominent drain cover!

 

The kitchen was delivered last week and should be installed next week. Here are some of the bits stored in the sun room. Outside the house, the huge piles of soil and rubble have been removed and the ‘garden’ has been levelled out. A concrete base has been poured for the patio but the stone slabs have not arrived yet.

The small pile of rocks at the right side of the house are ready for making repairs to the drystone walls. It looks like we’ll have to host a rock-picking party before we can seed the grass in the Spring.

We went for a stroll across the sands to Ardwall Island. The island is accessible on foot from the mainland for an hour or so at low tide.

Drains and Floors

We had a surge of activity in early November with lots of building people on site. The drains are all installed underground, with rain water draining to a soak-away at the front of the house and the house waste water drainage routed to a new septic tank.

20121112-145913.jpg
Here’s Gabrielle inspecting the septic tank. There’s a lot more of it under the ground. It looks like a lot of rock had to be removed to get it installed. You can also see the heat exchanger unit of the air source heat pump over by the wall of the house. That should be up and running this week, getting the house up to a comfortable temperature.

20121113-083538.jpg
This is the internal unit for the air source heat pump now installed in the utility room. The tank on the left is a buffer tank which is used to help the heating system work more efficiently by buffering up a supply of hot circulating fluid and avoid the heating system turning itself on and off too frequently. The hot water tank is inside the big white ‘ecodan’ unit.

 

 

 

20121113-090354.jpg
The water supply is now fully connected up inside the house. This is the plumbing at the main stop cock which will be behind the utility room sink when the cupboard and sink unit has been installed.

20121113-090719.jpg
The wood flooring is now installed in the bedrooms and living areas and is hopefully adequately protected from ongoing building work under the green plastic sheeting. This is the old cottage living room with the wood burning stove ready for re-installation back into the fireplace. The door on the left leads through to the master bedroom. The door on the right opens into the kitchen.

Smooth Walls

The building work continues but progress is slower than we would like. The walls are now all plastered and have a coat of white paint to seal them so we can get an impression of how the rooms will look. Here’s Gabrielle in the dining room; the original wood burner stove is behind her in the fireplace, ready for final installation. The doorway leads through to the master bedroom and bathroom. The window alcove on the left shows the thickness of the ‘Gypliner’ drywall insulation that has been added inside the original cottage walls to make it nice and cosy.

The water supply is now connected through into the utility room. It’s the blue pipe on the right of the picture. There will be a sink and the washer/dryer along that wall eventually, with fitted storage cupboards all along the opposite wall. The big silver pipes are the inlet and outlet for the heat-recovery ventilation system that is installed up in the roof space above the utility room. The pipes and the cables on the left will be connected to the air source heat pump which will hopefully be installed next week. The ceramic tiles for the bathrooms are also on site, stacked in the living room (above), so we hope to see some progress soon in the sanitary department.

There has not been a lot of change outdoors except for the installation of the foundations for the air source heat pump and the shed/wood store. The walls of the shed have been on site for a few months now so we are expecting to see them installed soon.

 

Plant Nursery


We have been taking cuttings of many of our favourite plants from the Turnamiddle House garden and we bring a few of them down to Craig Cottage on each visit. The nursery bed is filling up nicely now with hostas, geraniums and other assorted specimens.

Plaster Board

Living room plaster boardThe roofing is finally complete and the rain gutters are being installed. The cement render on the outside of the extensions to the original cottage has been applied. The pace of building progress is increasing now that the building is fully weather-proof. The under-floor heating pipes are buried under a concrete screed so we can get a better feel for what the eventual floor height will be like. Most of the new build part of the house now has plaster board installed and the plasterers will be on site soon to apply the finishing coat.

Evening Sunshine

RainbowWe arrived at the cottage on a Sunday evening with the low sunlight shining through some short, sharp rain showers.  The sun really brought out the colour of the cedar cladding and gave us an impressive rainbow as the showers moved off to the east. The exterior works should start soon and we will have paving and gravel around the house and a patio across most of the west side.

Lunchtime Paddling

High tide was at lunch time last weekend so we took our sandwiches out in the kayaks and paddled over to Knockbrex beach for lunch. There was a wind from the north west so it was a bit choppy on the way out towards Ardwall Island.

20120906-203928.jpg
On the return journey we stayed in the shelter of Ardwall Island before heading back past Barlocco Island with the wind behind us. We got a good view of Craig Cottage as we paddled up Kirkandrews Bay.

20120906-204443.jpg

Pipes

The under floor heating pipes have now been installed and there are rather a lot of them. This is the kitchen and sun room with spaces left for the kitchen island and cupboard units. The kitchen walls are now insulated and ready for plaster boarding once the floor screed has been laid.

20120906-200945.jpg
There will be 14 heating zones with one zone per room and a couple of extras to cover large floor areas. The picture below shows the main mass of piping heading down the hallway from the manifolds which will be in the cupboard by the main entrance.

20120906-201702.jpg
On the outside it’s been fairly wet but there has been progress on the slating and cedar cladding. The slating is complete apart from finishing round the original cottage chimneys and the cedar cladding is all done. Here’s a view of the mud bath outside the living room.

20120906-202517.jpg

More Slates and Cladding

Slating is progressing but there have been a few delays for the occasional torrential rain showers. The roof is nearing completion and looking rather good.

Garage Roof

Lots of shiny new slates and the zinc roof over the main door

Big yellow tractor

Cedar cladding, the zinc sun room roof and bedroom brickwork ready for harling

Garage Door

The garage door

All of the brickwork is now complete around the master bedroom, the new porch and the back side of the kitchen. The rough brick surfaces will now be covered with a smooth harl and finally painted to match the painted stonework of the original cottage. The cedar cladding is also nearing completion and just waiting for some final rain flashing around the bathroom window before the last cladding can be installed. The garage door is installed and the house can now be locked up although there are still some swallows flying in and out through the gap above the sun room windows. Inside the house, the under-floor insulation is in place and we are getting ready to lay the pipes for the underfloor heating. You can see the underfloor heating schematic on the plans page.

Roofing

The roof is getting its slates attached. This is how it looked earlier this week. Just in time before the next band of heavy rain arrives. Thanks to Graeme, our architect, for the picture. We will be on site again this weekend for a full update on progress.

Slates and sun room roofing

New slates and sun room roofing